A delayed cycle route creates problems for Kjell Inge Rokke’s office project at Fornebu, writes Dagens Næringsliv.

The offices will be ready for 1st June. A pedestrian and cycle path, which should have been completed on 22 May, however, is delayed and will not be ready before July 1. According to the so-called succession provision needs such a cycle path to be in place before it can be granted permission to use, and Aker have now therefore apply for an exemption.

See also: You can Røkke earn half a billion

– We are in dialogue with the municipality. I reckon that we get a dispensation so that we can keep to the schedule, says Akers property manager, Torstein Storækre, said.

According to DN, the application for exemption number 14 in a series of applications for exemptions relating to this construction project.